Off-Grid Countdown & Load Planner

Companion to Off Grid by Winter by Adam Wolf. The Countdown Worksheet from Chapters 1 and 9 and the load worksheet from Chapter 5, run on your own land. Nothing is stored; nothing leaves your browser.

1. Find your real deadlineFirst hard freeze, minus a buffer, minus the longest lead time you are carrying. That date, not the closing date, decides which phone call comes first (Chapter 1).
2. Size the power you actually needList only the loads that keep you alive and reachable. Daily watt-hours become an array, a battery and an inverter with the book's four lines of math (Chapter 5).
3. Replace the placeholdersEvery lead time here is illustrative. One afternoon of calls to your county and two or three drillers gives you real numbers; type them in and the dates move.
Example from the book:

Countdown (Chapters 1 & 9)

Your county extension office or the USDA hardiness map gives the average first hard freeze (28°F). Use the average, not the record.

Default three weeks: the permit that runs long, the delivery that slips, the week you lose to rain.

Lead times, in weeks (placeholders until you call)

Minimum-viable load (Chapter 5)

Nameplate watts × hours per day, or type the watt-hours straight in when you know them (a fridge's yearly label ÷ 365). Leave a row at 0 if you will not run it.

Site and hardware

Your Chapter 2 site number. Use the winter figure, never the brochure's summer one.

How many cloudy days the battery alone must carry.

Well pump or fridge compressor. The inverter is sized to its starting surge.